What are the conditions for the assignment of LOADLINE?

asked 10 Nov '18, 01:34

Nov. 10, 2018, 1:34 a.m.
KnowledgeBase's gravatar image


81263315422
accept rate: 0%


  • The vessel must be structurally adequate for the intended voyage.
  • The vessel has adequate stability for its intended service.
  • The vessel has a hull that is watertight from keel to freeboard deck and weather-tight above the freeboard deck.
  • The working area for the crew is high enough for safe movement of the crew during adverse weather or else catwalk or lifelines must be provided.
  • The vessel must have enough reserve buoyancy above the water line.
permanent link

answered 10 Nov '18, 01:35

Nov. 10, 2018, 1:35 a.m.
capt's gravatar image


11
accept rate: 0%

add your answer