MEG4 requires to identify SHIP'S DESIGN MBL and to record it in MSMP ''mooring system managment plan'' and also in LMP ''line mamagment plan''.

Hwo to calculate SHIP'S DESIGN MBL ? knowing that in our case the concerned ship was constructed and launched in 2007 where MEG 3 was in force.

asked 29 May, 11:59

May 29, 2019, 11:59 a.m.
OPSSHIP22's gravatar image


26101120
accept rate: 0%


Answer:

According to SHIPBOARD EQUIPMENT, FITTINGS AND SUPPORTING HULL STRUCTURES ASSOCIATED WITH TOWING AND MOORING:

[2.9​[Ship Design] Minimum Breaking Load ([MBL/MBLsd]) means the minimum breaking load of new, dry, mooring lines for which shipboard fittings and supporting hull structures are designed in order to meet mooring restraint requirements.]

Requested Ship’s design MBL details could be found in mooring equipment & fittings particulars/blueprints.

alt text

permanent link

answered 31 May, 05:07

May 31, 2019, 5:07 a.m.
capt's gravatar image


113
accept rate: 0%

edited 31 May, 12:22

add your answer

MarineProHelp 2018 - 2019.

First time here? Check out the FAQ!

×