How should cargo line segregation be arranged in case of two non-compatible products?

22 Jul '19, 19:48

July 22, 2019, 7:48 p.m.
marinexpert's gravatar image




Answer:

Double blank flanges with a drain between them should be installed.

permanent link

22 Jul '19, 19:55

July 22, 2019, 7:55 p.m.
marinexpert's gravatar image